Development Code for Data Centers
On June 2, 2026, the Statesboro City Council approved Ordinance 2026-01, an amendment to Section 2.4.14 of the Unified Development Code (UDC) establishing new zoning classifications and requirements for Technological Facilities and Data Centers. The ordinance passed 3-1 after a public hearing and months of research, including staff and council visits to existing data center sites in Georgia.
It's important to note: this ordinance does not approve any specific data center project. Instead, it creates the rules and process that would apply to any future proposal.
Why did the City consider this?
City leaders say the ordinance was meant to be proactive rather than reactive — putting clear, vetted rules in place before any project came forward, rather than negotiating standards after the fact. Council members have emphasized that the ordinance itself does not obligate the City to approve any project — each proposal still requires its own Special Use Permit review, public hearing, and council vote. Residents will have the opportunity to weigh in on any specific proposal, just as they did during the development of this ordinance.
Frequently Asked Questions
- Data centers vary by scale. Many people consider them all massive facilities (i.e., Effingham County) but they can substantially vary in size. The City of Statesboro caps all data center campuses to sites with at most 50 acres. The actual facility square footage is much lower due to the needs for buffers, stormwater, parking, and electrical generation.
- Data centers are notoriously connected to AI, but that isn’t actually what all facilities are for. A substantial number of facilities in the US are used for everyday task such as cloud services, banking information and streaming. [i]
[i] EPI Center for Scientific Evidence in Public Issues: March 2026 Data Center Article
[i] Public Service Commission Data Center Fact Sheet: March 2026
[i] https://future-bridge.us/noise-control-in-data-centers-key-design-strategies/
- They absolutely can consume significant water, but many facilities are working towards reducing their water impact in a number of ways. Many have moved to the use of closed-loop systems, which act similar to the radiator in a vehicle by recycling water within the system itself. Others are creating their own treatment facilities to reuse water on site. Older evaporative cooling technology can use enormous volumes of water.
- The City of Statesboro requires all data centers to hook to municipal sewer and water, preventing individual well impacts after construction.
[i] Tract Capital Management, LP: Data Centers and Residential Property Values March 2026
[i] Federal Reserve System: Beige Book: August 2026
[ii] Northern Virginia Technology Council, 2024 Data Center Biennial Report: April 2024
FAQ Sources
[i] EPI Center for Scientific Evidence in Public Issues: March 2026 Data Center Article
[ii] Public Service Commission Data Center Fact Sheet: March 2026
[iii] Future Bridge Acoustic Strategies for Noise Control in Data Centers
[iv] Tract Capital Management, LP: Data Centers and Residential Property Values March 2026
[v] Federal Reserve System: Beige Book: August 2026
[vi] Northern Virginia Technology Council, 2024 Data Center Biennial Report: April 2024